When a builder does not hand over a flat or plot by the date promised in the agreement, the Real Estate (Regulation and Development) Act, 2016 (RERA) gives the buyer a clear remedy before the Gujarat Real Estate Regulatory Authority (GujRERA) at Gandhinagar. This article explains the choices, the documents and the steps, so that you can decide calmly.

In short

  • If possession is delayed beyond the agreement, Section 18 lets you either leave the project and get your money back with interest, or stay and receive interest for every month of delay.
  • Complaints are filed online on the GujRERA portal; under the procedure introduced in December 2025 (as reported), a physical copy then goes to the RERA office within seven days.
  • Refund and interest are decided by the Authority; compensation claims go to the adjudicating officer.

Your two choices under Section 18

  • Withdraw from the project: the builder must return the amount paid, with interest at the rate prescribed in the rules, and compensation as provided in the Act.
  • Stay in the project: the builder must pay interest for every month of delay until possession is handed over.

The right choice depends on how much you have paid, whether the project is moving, your home loan and whether you still want this home. Get advice before deciding, because the choice shapes the complaint.

Before you file

  • Check the project page on the GujRERA portal: the declared completion date, the quarterly progress updates and any extension granted.
  • Write to the builder by email or letter asking for the possession date and the reason for the delay. Keep the reply, or note that none came.
  • Speak to other buyers in the project. Under the Explanation to Section 31(1), an association of allottees or a registered voluntary consumer association can also file a complaint.

Documents to keep ready

  • Registered agreement for sale (Banakhat) and allotment letter
  • Every payment receipt and the matching bank statement entries
  • Home loan sanction letter and tripartite agreement, if any
  • Brochure, advertisements and builder letters or emails about possession
  • Copies of the GujRERA project page

Filing the complaint

  • Section 31 allows a complaint to the Authority or to the adjudicating officer for a violation of the Act, the rules or the regulations.
  • Form A is used for matters such as delay in possession, non-execution of the sale agreement or refund. Form B is for compensation claims, which the adjudicating officer decides under Section 71.
  • Under the December 2025 procedure (as reported), the complaint and documents are filed online, a physical copy is submitted to the RERA office within seven days, and hearing dates, notices and orders appear on the RERA dashboard. Check the dashboard regularly after the first notice.
  • Check the current form, fee and procedure on the GujRERA portal before filing, because they can change.

After the order

  • If the builder does not pay the interest, refund or compensation ordered, Section 40(1) allows it to be recovered as arrears of land revenue.
  • An appeal against an order lies to the Gujarat Real Estate Appellate Tribunal under Section 44, generally within 60 days. Under Section 43(5), a builder who appeals must first deposit with the Tribunal at least 30% of any penalty, or the total amount payable to the buyer including interest and compensation, as the case may be.

What you can do today

  • Save a copy of the project page from the GujRERA portal.
  • Put the agreement, receipts and loan papers in one folder, in date order.
  • Write a short timeline: booking date, promised possession date, payments made and the builder's replies.

How long it may take

  • Collecting documents and preparing the complaint: allow two to three weeks, longer if papers are missing or the office is busy.
  • Hearings before GujRERA: plan for several months, often longer, depending on the number of hearings and the builder's replies.
  • Recovery after an order, or an appeal, can add more time.

These are approximate times, not promises. If it moves faster, that is a bonus.

Common questions

The builder offers a new date. Should I wait?

That is your choice. Your rights under Section 18 are linked to the date in your agreement, not to a new oral promise. Get any new date in writing, and keep your documents ready either way.

Can buyers of the same project complain together?

Yes. Besides individual buyers, the Explanation to Section 31(1) allows an association of allottees or a registered voluntary consumer association to file a complaint.

A delayed home is stressful, especially with a loan running. The law gives a clear route, and every step is on record. Keeping your papers in order is the most useful thing you can do now.

This article is general information about the RERA Act, 2016 and the GujRERA procedure. It is not legal advice for any particular case. Forms, fees and procedures change, so check the current position on the GujRERA portal and have your documents reviewed before filing.