The Real Estate (Regulation and Development) Act, 2016 (RERA) sets duties for builders, called "promoters" in the Act, and rights for buyers, called "allottees". In Gujarat, the Gujarat Real Estate Regulatory Authority (GujRERA) at Gandhinagar registers projects and hears complaints. The Act protects buyers best when a few things are checked before any money is paid.

In short

  • A project that needs RERA registration cannot be advertised, booked or sold without a GujRERA registration number.
  • Before a registered agreement for sale, the builder cannot take more than 10% of the price.
  • If possession is delayed, the Act gives you a choice: a refund with interest, or interest for every month of delay.

1. Is the project registered?

Under Section 3, a builder cannot advertise, market, book or sell apartments or plots in a project without first registering it with the authority. Small projects are exempt: land of up to 500 square metres, or up to eight apartments across all phases.

  • Ask for the GujRERA registration number. Section 11(2) requires every advertisement and brochure to show it, together with the authority's website address.
  • Search the number on the GujRERA portal and match the project name, builder name, address and survey or plot numbers with the brochure.
  • If a project that needs registration has no registration number, treat it as a warning sign.

2. Read the project page on the portal

Section 11(1) requires the builder to keep the project's web page on the authority's website updated every quarter. Check:

  • the sanctioned plans and the layout of your wing or block;
  • the completion date the builder has declared to the authority;
  • how many units are booked and the status of approvals;
  • the quarterly progress updates.

Compare the completion date on the portal with the date written in your agreement.

3. Carpet area

Section 2(k) defines carpet area as the net usable floor area of an apartment. It excludes the external walls, service shafts and any exclusive balcony, verandah or open terrace, but includes the internal partition walls. Make sure the carpet area is written in the agreement and the price breakup, and do not compare prices on "super built-up" figures alone.

4. Pay no more than 10% before a registered agreement

Under Section 13(1), a builder cannot take more than 10% of the cost of the apartment or plot as an advance or application fee before entering into a written agreement for sale and getting it registered. Pay by bank transfer or cheque and keep every receipt.

5. Where your money goes

Section 4(2)(l)(D) requires the builder to deposit 70% of the amounts collected from buyers in a separate bank account, to be used only for the land and construction cost of that project. Withdrawals from that account need certificates from an engineer, an architect and a chartered accountant.

6. Brochures and sample flats

Under Section 12, if a buyer suffers loss because of an incorrect statement in an advertisement, brochure or model apartment, the builder must compensate the buyer. A buyer who chooses to withdraw from the project can get the amount paid back with interest and compensation. Keep a copy of the brochure and photographs of the sample flat.

7. After you book

  • Changes to plans: Section 14 requires the builder to follow the sanctioned plans. Apart from the minor changes the Act allows, other changes need the written consent of at least two-thirds of the allottees.
  • Transfer of the project: under Section 15, the builder cannot transfer the majority of its rights in the project to someone else without the written consent of two-thirds of the allottees and the prior written approval of the authority.
  • Delay: under Section 18, if possession is not given as per the agreement, the buyer may withdraw and get a refund with interest and compensation, or stay in the project and receive interest for every month of delay until possession.
  • Possession: under Section 19(10), the buyer must take possession within two months of the occupancy certificate being issued.
  • Defects: under Section 14(3), a structural defect or a defect in workmanship, quality or services reported within five years of possession must be rectified by the builder within 30 days at no cost. Otherwise the buyer is entitled to compensation.

Where to complain

A complaint can be filed online on the GujRERA portal under Section 31. Claims for compensation are decided by the adjudicating officer under Section 71. An appeal against an order lies to the Gujarat Real Estate Appellate Tribunal under Section 44, generally within 60 days.

Quick checklist

  • Registration number found and matched on the GujRERA portal
  • Completion date on the portal matches the agreement
  • Carpet area written in the agreement
  • No more than 10% paid before a registered agreement
  • Brochure and sample-flat photographs saved
  • All payments made through a bank, with receipts

What you can do today

  • Search the project's registration number on the GujRERA portal and save a copy of the project page.
  • Keep the brochure, every payment receipt and the draft agreement together in one folder.
  • Compare the completion date the builder told you with the date on the portal and in the agreement.

How long it may take

  • Checking the project on the GujRERA portal yourself: usually the same day.
  • Getting the draft agreement and title papers checked: allow two to three weeks. It depends on the documents and on how busy the office is.
  • A complaint before GujRERA: plan for several months, sometimes longer, depending on hearings and the builder's replies.

These are approximate times, not promises. If the work finishes earlier, that is a bonus.

Common questions

The builder says registration is "in process". Can I book now?

Under Section 3, a project that needs registration cannot be booked or sold until it is registered. Wait until the registration number appears on the GujRERA portal.

Possession is late. Must I leave the project to get anything?

No. Under Section 18 you may stay in the project and receive interest for every month of delay, or withdraw and get a refund with interest and compensation.

Checking these points early puts a buyer in a much stronger position. Keep the papers together and take one step at a time.

This article is general information about the RERA Act, 2016. It is not legal advice for any particular case. Facts and documents differ from one property to another, so have the agreement and the title checked before paying.